Allocate Directly on Work Task
Explanation
- Use this activity when you quickly want to allocate a resource to
one or multiple work tasks and no resource demands have been
specified.
Prerequisites
System Effects
- As a result of this activity, work assignments will be created for the resources and the work task will be
considered allocated. Each work assignment will get an Allocated Start and Allocated Finish. The work
assignment will be assigned to a resource and its status will be set to Assigned.
- If Adjust to Schedule check box is selected, then the
Allocated Start and Allocated Finish are adjusted based on the working schedule of the resource.
- The Allocated Start and Allocated Finish dates will be set from the Planned Start
and Planned Finish. If Duration is entered on the
Work Task it will be used as default value for Allocated Hours.
When using Allocate Resource to Multiple Tasks
and if no dates are set, the system date is used for Allocated Start.
Window
Work Task
Work Tasks
Prepare Work
Order
Work Order
Structure
Related Window Descriptions
Assign Work
Work Task
Prepare Work Order
Work Order Structure
Procedure
Read about:
- Open the Assign Work dialog box. This can be done in
three ways:
- Right-click a record in Active Work
Orders or Work
Tasks and click Assign Work
- Right-click the header in Prepare Work
Order or Work Task and click
Assign Work
- Right-click one or multiple records in Prepare Work Order/Work Tasks and click Assign Work
- If the selection included multiple work tasks you use the Task No list to
choose the work task to create assignments for.
- Go to the Direct Allocation tab.
- Click the plus sign (+) in the table to create a new allocation record.
- Click to select Allocated To and click the List... button to display the List of Values
that contains resources that are eligible for the work task site.
- Select the resource that should be assigned click OK.
- Enter the start and finish time of the allocation in Allocated Start and Allocated Finish.
- Enter the duration of the allocation in Allocated Hours.
- Click Save to save the allocation.
- To remove an allocation record select it and click Remove.
- Click Save.
- Open the Assign Work dialog box. This can be done in
three ways:
- Right-click a record in Active Work
Orders or Work
Tasks and click Assign Work...
- Right-click the header in Prepare Work
Order or Work Task and click
Assign Work...
- Right-click one or multiple records in Prepare Work Order/Work Tasks and click Assign Work...
- If the work order or service request selection included multiple work tasks you use the Task No list to
choose the work task to create assignments for.
- Go to the Direct Allocations tab.
- Click the plus sign (+) in the table to create a new allocation record.
- Click to select Allocated To and click the List... button to display the List of Values
that contains resources that are eligible for the work task site.
- Select the resource that should be assigned click OK.
- Enter the start and finish time of the allocation in Allocated Start and Allocated Finish.
- Enter the duration of the allocation in Allocated Hours.
- Click Save to save the allocation.
- Select Adjust to Schedule check box
- To remove an allocation record select it and click Remove.
- Click Save.
- Open the Assign Multiple Tasks dialog box. This can be done in three ways:
- Select multiple records in Active Work Orders or Work Tasks
and right-click and click Assign Multiple Tasks...
- Right-click the header in Prepare Work Order or Work Task and click Assign Multiple Tasks...
- Select one or multiple records in Prepare Work Order/Work Tasks and right-click and click Assign Multiple Tasks...
- Select Resource Type.
- Click to select Resource ID and click the List... button to display the List of Values that
contains resources that are eligible for the work tasks site.
- Select the resource that should be assigned click OK.