Use this dialog box to register that the downtime has started on a work center resource. Downtime is used to measure and classify periods during which a work center resource is unavailable due to causes such as tool breakage, worker unavailability, machine breakdown etc.
Note: Downtime can be started for any of the work center resources valid for the filter currently entered in the shop floor workbench header section using this dialog box.
Report machine downtime from shop floor workbench