Analyze Project Exceptions
Explanation
This activity describes how to analyze project exceptions. The analysis aims
to detect problems which the activity or its connected objects might have at the
time of the evaluation, and includes:
- Checking if the activity budget has been
exceeded.
- Checking if critical deliveries and work can be achieved on time.
- Evaluating the progress and need date of the activity connected objects.
To help with the above analysis, the following conditions are automatically
presented as an Activity Exception:
- Resource planning has un-spread hours or missing price
-
Committed
+ Used Cost exceed Planned Cost
-
Committed + Used Hours exceed Planned Hours
- Connected orders that are planned/due to be executed late
The Gantt chart gives a visual help to analyze activity exceptions. It is possible to:
- View activities with exceptions.
- View time-critical objects connected to an activity, making it easy to
determine if any such connected object has a need or required
date that fall outside the activity's early start and early finish dates. The objects
that can be seen in the Gantt chart are Purchase Order line, Shop Order, Work Order
and DOP Header.
Prerequisites
N/A
System Effects
N/A
Window
Project Navigator/Connections
Activity/Connections
Gantt
Project Exceptions
Activity
Exceptions
Related Window Descriptions
Project Navigator/Connections
Activity/Connections
Project Connections
Gantt
Project Exceptions
Activity Exceptions
Procedure
Analyze activity connected objects in
the Project
Navigator/Activity/Connections
tab:
- Select the desired activity.
- Select each object connection line.
- Observe the cost and progress information for each object.
- Alternatively in the Project Navigator/Activity/Cost, Hours
and Revenue tabs, select the desired rows, right-click
and click the Project Connections menu option to view the relevant records in
the Project Connections
window.
Analyze activity connected objects in the
Gantt
window:
- Observe if there is a warning triangle to the left of an activity, indicating
that there is a exception for that activity.
- To view the exception details, right-click
the activity bar and select
the menu option Activity Exceptions.
- In the Gantt window, select an activity with connected objects.
Right-click and select the Show Activity Connections menu option.
- Time-critical objects (Purchase Order line, Shop Order, Work Order and DOP
Header) connected to the activity will be indicated by icons
or bars in the Gantt chart.
- To view details of a particular object, right-click the icon and select
the relevant menu option. I.e. Purchase Order Line, Shop Order, Work
Order or DOP Header.
Analyze activity connected objects in either the
Project Exceptions or
the Activity Exceptions
window:
- Query the project.
- Go to the relevant tabs and evaluate the records.
Analyze activity connected objects in the
Project Connections
window:
- Query the desired records to be analyzed. For example, it is possible to
query a project ID, specific activities, object types or project cost elements.
- Observe the costs (estimated, planned, baseline, planned committed, committed,
used and actual) per connected object and per project cost element.