Create Supply Request for Purchase Order Plan
Explanation
Use this activity to create supply request for purchase order plans. A
recommendation is to review material plan warnings before creating the supply
request: Review Material Plan
Warnings.
Prerequisites
- A purchase order plan should exist. A purchase order plan is created during the
creation of material plans, as described here:
Generate Material Plan
- Previously created supply requests should not exist.
- Deliverable items must be approved.
- Project activity must be released.
System Effects
A purchase requisition is created.
Window
Project
Deliverables Navigator
Related Window Descriptions
Project Deliverables
Navigator/Materials/Material Plans
Project
Deliverables Navigator/Shop
Order Plan/General
Procedure
Create many supply requests in the Project Deliverables/Materials/Material
Plans tab:
- Open the Project Deliverables Navigator window and populate it with
values.
- Click the Materials tab and then the Material
Plans tab.
- Select one or many records that have Purchase as the supply
option.
- Right-click and then click Create Supply Request.
- Press OK and confirm the dialog box that appears.
Purchase requisition and purchase order can now be further processed, as described here:
Initiate Purchase
and Manage Purchase.
Create a single supply request in Project Deliverables/Purchase Order
Plan/General tab:
- Open the Project Deliverables Navigator window and populate it with
values.
- Expand the structure and navigate to a purchase order plan.
- Right-click on the Purchase Order Plan/General tab and
then click Create Supply Request.
- Right-click and then click Create Supply Request.
- Press OK and confirm the dialog box that appears.
Purchase requisition can now be further processed, as described here:
Initiate Purchase
and Manage Purchase.