Explanation
Use this activity to create shipment plans. A shipment plan can be created in
two different ways:
- Manually created for one single item.
- Automatically created for a complete structure.
Prerequisites
Item should have been defined with an inventory part and gross requirements
should have been calculated to get the correct quantities and dates:
Generate Material Plan. The automatic creation
of shipment plans requires a top phantom item to be created. The phantom item's
component structure, must have been defined with inventory parts.
The same material can be added on several work task plans and shipment plans
as longs as the total required quantity isn't exceeded. The total required
quantity is calculated when gross requirement calculation is run. The quantity
for the same material can be balanced between shipment plans and work task
plans, so that it doesn't exceed the total required quantity:
- Modify quantity on a shipment plan in Project Deliverables
Navigator/Planning Items tab and enter a quantity that doesn't
exceed the total required quantity.
- Modify quantity on a work task plan in Work Task
Plan/Materials tab and enter a quantity that doesn't exceed
the total required quantity.
Information about how to manage material on work task plans are described
here: Manage Materials on
Work Task Plan.
System Effects
None
Window
Project
Deliverables Navigator
Related Window Descriptions
Project Deliverables Navigator/Planning Items
Project Deliverables Navigator/Shipment Plans/Shipment Plans
Project Deliverables Navigator/Shipment Plan/General
Project Deliverables Navigator/Shipment Plan/Shipment Parameters
Procedure
Manually create a shipment plan:
- Open the Project Deliverables Navigator window and populate it with
values.
- Open the Planning Items tab.
- Create a new record and select execution type Shipment.
- Enter a planning item name.
- Save the record and notice how a shipment plan is shown in the tree.
- Select the shipment plan and
open the General tab or select the item and
open Project Deliverables Navigator/Shipments/Shipment Plan
tab.
- Enter Customer ID and Shipment
Type or select from List of Values.
- Enter optional information about planned ship date,
planned delivery data etc.
- Save the record.
- Select shipment plan, in the tree and
open the Shipment Parameters tab.
- Enter optional information about forward agent ID,
delivery terms etc.
- Save the record.
Create shipment plans for a structure:
- Open the Project Deliverables Navigator window and select
a phantom item.
- Make sure that the phantom item has an underlying component structure
and where components are defined with inventory parts.
- Open Shipments /Shipment Plans tab.
- Right-click and then click Create Shipment Plans.
- The number of created shipment plans are shown in a dialog.
- Click OK and review the created the created shipment plans.
- Enter Customer ID and Shipment
Type or select from List of Values.
- Enter optional information about planned ship date,
planned delivery data etc.
- Save the record.
- Select shipment plan, in the tree and
open the Shipment Parameters tab.
- Enter optional information about forward agent ID,
delivery terms etc.
- Save the record.