Use this window to manually spread and verify it per day. The Estimated to Complete (ETC) hours per date have to be manually entered into the table and the result is immediately shown in the graph.
The window shows one single resource forecast row consumption.
The information displayed is the resource row usage spread across all the work days available, according to the calendar for the resource group. The graph displays a day period, starting with the work day closest to the early start date of the connected activity. You can scroll through the entire activity period and view the resource allocation changes. This is useful to identify over allocated resources as you add resource connections to your project.
The bar shown for each day is the total usage allocated for the work day on the X-axis.
The normal capacity limit defined for each day for the resource group is displayed as a line in the graph. This shows you how your estimated resource usage relates to available resources.