Distribute Cumulative Forecast

Explanation

This activity is used to distribute the cumulative forecast of an MS level 0 or MS level 1 part.

Prerequisites

MS set should be defined for selected MS level 0 or MS level 1 part.

System Effects

As a result of this activity, the system creates forecast lines for the selected date interval.

Window

MS Level 0 Part
MS Level 1 Part

Related Window Descriptions

Distribute Cumulative Forecast
MS Level 0 Part
MS Level 1 Part

Procedure

  1. Right-click on the MS Level 0 Part/Register Forecast tab or MS Level 1 Part/Register Forecast tab and then click Distribute Cumulative Forecast.
  2. Enter values in the From Date and To Date fields.
  3. Enter value in the Cumulative Forecast field.
  4. Select forecast distribution method Daily, Weekly or Monthly.
  5. Select Calendar ID using List of Values.
  6. Click OK.