Production Scrap

Explanation

This activity is used to declare scrap that occurred on the produced parts during the manufacturing process. For catch unit enabled parts, if the parent part comprises of one or more catch unit (CU) enabled components, the CU enabled components have to be reserved before backflush is performed.

Note:
Labor and operation setup time for each receipt is calculated as;
[(setup time/standard lot size)*receipt quantity]
If standard lot size is not defined, then the total setup time will be reported for every receipt. 

Prerequisites

System Effects

Window

Production Receipt
Production Schedule by Line
Production Schedule by Line Part
Production Line Management

Related Window Descriptions

Production Receipt
Production Schedule by Line
Production Schedule by Line Part

Production Line Management
Production Line Management/Current Production Schedule Scrap Receipt

Procedure

From the Production Receipt window:

  1. Open the Production Schedule window.
  2. In the Production Line list, select the production line and part for which to report scrap.
  3. Right-click and then click Scrap Receipt. The Scrap Receipt dialog box appears.
  4. In the Scrap Receipt dialog box, Select the Receipt in Background check box to execute the receipt in the background .
  5. In the Sched Option list, select Scheduled to consume from the quantity scheduled, or Unscheduled to not consume from the scheduled quantity.
  6. In the Structure area, specify the structure revision and structure alternate. If desired, also specify the routing revision and the routing alternate.
  7. In the Production Scrap area, type the quantity scrapped in the Qty Scrapped field. Click in the Scrap Reasons field, then click List to select from available scrap reasons. If the part is catch unit enabled, the catch quantity should also be entered. 
  8. In the Report Point area, select the Complete Scrap check box to specify that this is the complete scrap for the manufacturing process.
  9. Click OK.

From the Production Schedule by Line or Production Line Management/Current Production Schedule window:

  1. Search for the production line.
  2. Select the production schedule line for which you want to report scrap. Right-click and then click Scrap Receipt. The Scrap Receipt dialog box appears.
  3. In the Scrap Receipt dialog box, Select the Receipt in Background check box to execute the receipt in the background
  4. In the Sched Option list, select Scheduled to consume from the quantity scheduled, or Unscheduled to not consume from the scheduled quantity.
  5. In the Structure area, specify the structure revision and structure alternate. If desired, also specify the routing revision and the routing alternate.
  6. In the Production Scrap area, type the quantity scrapped in the Qty Scrapped field. Click in the Scrap Reasons field, then click List to select from available scrap reasons. If the part is catch unit enabled, the catch quantity should also be entered in the Catch Qty Scrapped field.  
  7. In the Report Point area, select the Complete Scrap check box to specify that this is the complete scrap for the manufacturing process.
  8. Click OK.

From the Production Schedule by Line Part window:

  1. Search for the part.
  2. Select the production schedule line for which you want to report scrap. Right-click and then click Scrap Receipt. The Scrap Receipt dialog box appears.
  3. In the Scrap Receipt dialog box, Select the Receipt in Background check box to execute the receipt in the background .
  4. In the Sched Option list, select Scheduled to consume from the quantity scheduled, or Unscheduled to not consume from the scheduled quantity.
  5. In the Structure area, specify the structure revision and structure alternate. If desired, also specify the routing revision and the routing alternate.
  6. In the Production Scrap area, type the quantity scrapped in the Qty Scrapped field. Click in the Scrap Reasons field, then click List to select from available scrap reasons. If the part is catch unit enabled, the catch quantity should also be entered in the Catch Qty Scrapped field. 
  7. In the Report Point area, select the Complete Scrap check box to specify that this is the complete scrap for the manufacturing process.
  8. Click OK.