Production Receipt with Catch Unit Components
Explanation
This activity is used to report production has been completed and received
into inventory from a production schedule for a part with catch unit enabled
components. A catch unit is enabled to allow a specific
inventory part to manage two parallel units of measure. Information regarding
both quantities, inventory and catch, are saved on every inventory transaction
record.
Prerequisites
- A part can be reserved as a catch quantity only if it
is catch unit enabled.
- If catch unit is enabled for the parent
part, the quantity reported must have been entered in both the inventory unit of
measure (UoM) and catch UoM.
- The structure alternate cannot be a rework alternate.
System Effects
- The reserved quantities in both the catch UoM and
inventory
UoM will be issued during backflush.
- Inventory locations will be updated with issued and received quantities.
Window
Production
Receipt
Production
Schedule By Line
Production Schedule By Line Part
Production Line
Management
Related Window Descriptions
Production Receipt
Production Schedule by Line
Production Schedule by Line Part
Production Line Management
Production Line Management/Current Production Schedule
Procedure
From the
Production Receipt window:
- Search for the production line and part.
- In the Sched Option list, select Scheduled
to consume from the quantity scheduled, or Unscheduled to
not consume from the scheduled quantity.
-
In the
Structure area,
specify either the the structure/routing revision, or the
structure/routing alternate.
-
If you want the receipt to be executed as a background job, select the
Receipt in Background check box.
- In the table section, create a new record and enter the quantity to
receive in the Qty Received field.
- In the Location No field, select the location to which
the parts should be received, or use the List of values to select available
inventory locations.
-
If the part is catch unit enabled, the catch quantity should also be
entered in the Catch Quantity Received field.
-
Select the Edit Components
check box and save, the
Production
Receipt Material dialog box appears.
-
To change the quantity to issue, enter the desired
value in Qty to Issue field.
-
Save.
-
To reserve the components before backflushing, select
the component and then click
Assign. The
Production
Receipt Reservation dialog box appears.
-
In the
Production Receipt Reservation
dialog box, click Create. The
Inventory Part Location
dialog box appears.
-
In the
Inventory Part Location
dialog box, select a location and click
OK.
-
In the
Production Receipt Reservation
dialog box, enter a value in the Qty Assigned field. Also enter the catch
quantity that you want to reserve in the Catch Qty Assigned field.
-
Save and then
click OK when the reservations are done.
-
When you have finished editing and reserving the components, click
OK to run the backflush.
From the Production Schedule by Line or Production
Line Management/Current Production Schedule window:
- Search for the production line.
- Select the production schedule line for which you want to report a
production receipt, right-click and then click Production Receipt,
the Production Receipt dialog box appears.
- Enter the quantity of parts to report and receive into inventory in the
Qty Reported field. The scheduled quantity is the default
value. If the part is catch unit enabled, the catch quantity should also be
entered in the Catch Qty Reported field.
- In the Sched Option list, select Scheduled
to consume from the quantity scheduled, or Unscheduled to
not consume from the scheduled quantity.
-
If you want the receipt to be executed as a background job, select the
Receipt in Background check box.
-
In the
Structure area, specify the structure revision and the structure alternate. If desired,
you can specify the routing revision and the routing alternate.
-
In the
Location area, select the
Complete check box to create a complete production receipt.
-
In the
Location area, click
in the
Location No field and then click
List to choose from different
inventory locations.
-
To edit components, click
Components. The
Production Receipt Material dialog box appears.
-
In the
Production Receipt Material
dialog box, type a value in the Qty To Issue field.
-
To change the components, click
New. In the Part To Issue
field, enter or select an available part from the List of Values. Next,
enter a value in Qty to Issue field.
-
Save.
-
To reserve the components before backflushing, select
the components and then click
Assign. The
Production
Receipt Reservation dialog box appears.
-
In the
Production Receipt Reservation
dialog box, click Create. The
Inventory Part Location
dialog box appears.
-
In the
Inventory Part Location
dialog box, select a location. Click
OK.
-
In the
Production Receipt Reservation
dialog box, enter a value in the Qty Assigned field. Also enter the catch
quantity that you want to reserve in the Catch Qty Assigned field.
-
Save and then
click OK when the reservations are done.
-
When you have finished editing and reserving the components, click
OK to run the
backflush.
From the
Production Schedule By Line Part window:
- Search for the part.
- Select the production schedule line for which you want to report a
production receipt, right-click and then click Production Receipt,
the Production Receipt dialog box appears.
- Type the
quantity of parts to report and receive into inventory in the Qty
Reported field. The scheduled quantity is the default value. If the part
is catch unit enabled, the catch quantity should also be entered in the
Catch Qty Reported field.
- In the Sched Option list, select Scheduled
to consume from the quantity scheduled, or Unscheduled to not
consume from the scheduled quantity.
- If you want the receipt to be executed as a background job, select the
Receipt in Background check box.
-
In the
Structure
area, specify the structure revision and the structure alternate. If you
want,
you can specify the routing revision and the routing alternate.
-
Select the Complete check box to create a
complete production receipt.
-
In the
Location area, click
in the
Location No field and then click
List
to choose from different
inventory locations.
-
To edit the components, click
Components. The
Production Receipt Material dialog box appears.
-
In the
Production Receipt Material
dialog box, enter a value in the Qty To Issue field.
-
To change the components, click
New. In the Part To Issue
field, enter or select
an available part from the List of Values. Next,
enter a value in Qty to Issue field.
-
Save.
-
To reserve the components before backflushing, select
the components and then click
Assign. The
Production
Receipt Reservation dialog box appears.
-
In the
Production Receipt Reservation
dialog box, enter a value in the Qty Assigned field. Also enter the catch
quantity that you want to reserve in the Catch Qty Assigned field.
-
Save and then
click OK when the reservations are done.
-
When you have finished editing and reserving the components, click
OK
to run the backflush.