Attach Parts to Handling Units for Production Schedule Receipt

Explanation

Use this activity to attach the parts to be received into handling units. The parts to be received will be automatically matched to a handling unit on the lowest level in the structure respecting the calculated quantity to attach. If required, you can manually move parts between the handling units to make sure it reflects how the finished goods have been physically packed.

The icons in the tree structure will indicate the quantity attached to the handling unit relative to the planned quantity to attach:

No quantity from this receipt has been attached to the handling unit or the handling units below it.
A quantity from this receipt has been attached to the handling unit and/or the handling units below it. However, the accumulated quantity attached is less than the accumulated max capacity for the handling unit.
The accumulated quantity attached for this handling unit and the handling units below, is equal to the accumulated max capacity for the handling unit.
The accumulated quantity attached for this handling unit and the handling units below, is higher than the accumulated max capacity for the handling unit.

Prerequisites

To perform this activity, packing instruction should have been defined for the production schedule receipt.

System Effects

As a result of this activity:

Window

Production Schedule by Line
Production Schedule by Line Part
Production Line Management

Related Window Descriptions

Production Schedule by Line
Production Schedule by Line Part
Production Line Management
Production Line Management/Current Production Schedule

Production Receipt
Attach Parts to Handling Units for Receipt
Move Qty to Handling Unit

Procedure

From Production Schedule by Line window:

  1. Search for the production line from which you want to pack and receive.
  2. Right-click and select Production Receipt.
  3. Press OK and the Attach Parts to Handling Units for Receipt dialog box will be automatically opened. Part records to be received have been automatically distributed to the handling units respecting their max capacity.
  4. Review how system has distributed the parts to be received to the handling units by using the tree structure. If required, re-arrange the assignments either by using drag-and-drop directly in the structure, or by using the Move button. The Move Qty to Handling Unit dialog box will appear.
  5. Enter the quantity to move in the Qty to Move field. If the part is catch quantity handled, enter the catch quantity in the Catch Qty to Move field. Click OK.
  6. If you want serial shipping container code to be generated, select the Create SSCC(s) check box.
  7. If you want labels to be printed, select the Print Handling Unit Label(s) and/or the Print Handling Unit Contents Label(S) check boxes.
  8. Click OK.

From the Production Schedule by Line or Production Line Management/Current Production Schedule window:

  1. Search for the part that you want to pack and receive.
  2. Right-click and select Production Receipt.
  3. Press OK and the Attach Parts to Handling Units for Receipt dialog box will be automatically opened. Part records to be received have been automatically distributed to the handling units respecting their max capacity.
  4. Review how the system has distributed the parts to be received to the handling units by using the tree structure. If required, re-arrange the assignments either by using drag-and-drop directly in the structure, or by using the Move button. The Move Qty to Handling Unit dialog box will appear.
  5. Enter the quantity to move in the Qty to Move field. If the part is catch quantity handled, enter the catch quantity in the Catch Qty to Move field. Click OK.
  6. If you want serial shipping container code to be generated, select the Create SSCC(s) check box.
  7. If you want labels to be printed, select the Print Handling Unit Label(s) and/or the Print Handling Unit Contents Label(S) check boxes.
  8. Click OK.