Copy Routing Alternate

Explanation

Use this activity to copy a specific routing alternate to a specific routing alternate on a pre-existing routing revision.

Prerequisites

This activity requires that the routing for which you want to create an alternate must have been created.

System Effects

As a result of this activity, the system copies a specific routing alternate to a specific routing alternate on a preexisting routing revision. Tool usage information is copied. No serial pointers are copied. These must be manually defined by the user. No work guidelines are copied. If the new alternate contains operations, the alternate will be set to the default state, as defined in Site/Manufacturing. If you check the Copy Attached Documents check box you will also copy documents attached to Routing Alternate and Routing Operation to the new alternate. The default value for this check box will be stored in the user profile.

Window

Routings
Routing Alternates

Related Window Descriptions

Copy Alternate
Routing
Routing/Routings
Routing Alternates

Procedure

  1. Select the part and the source routing alternate.
  2. Right-click in the Routings tab, then click Copy Alternate.
  3. In the Destination Alternate group box, click List to select the destination part in the Part No field.
  4. In the Destination Alternate group box, select the revision number in the Revision No field. Click List to select from existing revisions.
  5. Enter the alternate number in the Alternate field in the Destination Alternate group box.
  6. In the Destination Alternate group box, click List to select the site to which you are copying.
  7. Select Routing Type from the List box in the Destination Alternate group box.
  8. Click OK.