Reset Status of Purchase Requisition Header or Line to Planned

Explanation

This activity is used to change the status of a released purchase requisition or a requisition line to Planned.

Prerequisites

The purchase requisition or requisition line must have Released status.

System Effects

As a result of this activity, the purchase requisition or requisition line is demoted from Released to Planned status.

Window

Prepare Work Order

Related Window Descriptions

Prepare Work Order
Prepare Work Order/Requisitions
Prepare Work Order/Requisitions/Part Requisition Lines
Prepare Work Order/Requisitions/No Part Requisition Lines
Prepare Work Order/Requisitions/Rental Part Requisition Lines

Procedure

Use the following procedure to demote a requisition line to Planned:

  1. Click the Requisitions tab and query for the applicable purchase requisition number.
  2. Click the Part Requisition Lines, No-Part Requisition Lines or the Rental Part Requisition Lines tab and select the requisition line to be demoted. If required, you can also select several lines.
  3. Right-click and then click Change to Planned. The status of the line is changed back to Planned.

Use the following procedure to demote an entire requisition to Planned:

  1. Click in the header of the Requisitions tab.
  2. Right-click and then click Change to Planned. The status of the header and all lines is changed to Planned.