Enter Purchase Requisition Header

Explanation

Entering purchase requisitions is a preliminary step in creating purchase orders and can be considered a proposal to the buyer or coordinator for what is needed. Anyone who is entered as a requisitioner can create a requisition (a purchase order, by contrast, can only be issued by authorized personnel). Requisitions are also used to match supplier invoices.

A purchase requisition is built in two levels: a requisition header and one or several requisition lines. Use this activity to create a requisition header for an inventory part (including external maintenance and repair services), a non-inventory part, and external craft that is needed for a work order.

The requisition number is assigned by the system when you save the requisition. You cannot manually enter a requisition number.

The Create Request for Quotation check box in the Work Order Tender box is used when inviting business-to-business contractors to tender on the work order. If this check box is selected, a request for quotation is automatically created and released when a part or no-part line is released for this requisition. There can be only one requisition line (either a part or a no part requisition line) per work task to tender. You can still enter multiple requisition lines for the same work task on other requisition headers but Create Request for Quotation check box can not be selected.

Prerequisites

System Effects

As a result of this activity, a purchase requisition header with Planned status is created.

Windows

Prepare Work Order
Work Order Structure

Related Window Descriptions

Prepare Work Order
Prepare Work Order/Requisitions

Work Order Structure
Work Order Structure/Requisitions

Procedure

  1. Open the Prepare Work Order window or the Work Order Structure window and query for the applicable work order number.
  2. Click the Requisitions tab and create a new record.
  3. In the Requisitioner field, enter the applicable requisitioner or select one from the List of Values.
  4. The Site field shows the user's default site.
  5. Today's date is automatically displayed in the Requisition Date field.
  6. For items to be sent out for external service, select the External Service check box at the time of creating requisition header. This automatically assigns order code 6 (External Service Order) to the purchase requisition. After saving the requisition header you cannot select the checkbox, still you can change order code manually.  If the order code is 6 (External Service Order) you need to enter an external service type on the Part Requisition Lines tab when you complete the purchase requisition line.
  7. In order to invite contractors to tender on the work order, select the Create Request for Quotation check box, enter a date in the Latest Reply Date field and select a value in the Approved Contractor List field.
  8. Save the record. A requisition number is automatically assigned by the system and is shown in the Requisition No field. Note: The requisition header must be saved before any requisition lines can be entered.
  9. Once saved, the requisition header has Planned status.
  10. If you want to enter another requisition header for the same work order, create a new record and enter the required information.
  11. Save the record.