Verify Date Required - Material and Requisitions

Explanation

This activity is used to verify required dates for material and requisitions on a work order. When you have specified planned start and completion dates on a work order, the required dates for material issues are determined consequently. If you enter a new material item now, the planned start date is automatically suggested as the required date for the material. You can still remove or change the date. Before you carry on and release the work order, you should verify that the required dates for material and requisitions are not later than the planned start date.

Prerequisites

Before the information is verified, the following must have been completed:

System Effects

As a result of this activity, the required dates for material and requisitions are verified.

Window

Prepare Work Order

Related Window Descriptions

Prepare Work Order

Procedure

Use the following procedure to verify the information on the work order:

  1. In the Prepare tab, check planned start and completion dates, in the Start and Completion fields.
  2. In the Materials tab, check required dates for all material items, in the Date Required field.
  3. In the Requisitions tab, check required dates for all material items, in the Wanted Receipt Date field.