Explanation

Use this activity to update relevant work assignments with changes coming from the scheduled plan from Planning and Scheduling Optimization (PSO). By performing this activity work assignments will be updated with the latest scheduled plan from PSO. The fields that can be updated on the work assignment is Allocated Start, Allocated Finish and Duration.

When a work assignment is created by a commit from PSO or by the SDS it will be created with the data in the plan from where it was committed. If there has been changes to the activity in the coming plans after the commit, this will be denoted on the allocation record from the suggested plan by that the check-box Plan Changes will be set on the allocation. The allocation records can be found in Service and Maintenance/Work Task Management/Scheduled Work Tasks or in Service and Maintenance/Work Task Management/Work Task/Scheduling/Allocation

To update the work assignment to the information provided in the latest plan select the option Update Plan Changes from the right mouse button option available on such allocations.

it is also possible to set up a Scheduled Dataset Task to continuously run the Update Plan Changes function for allocations that has been changed after they were committed.

Prerequisites

System Effects

As a result of this activity, work assignments on the work task will be updated with the information from the latest scheduled plan from PSO.

Window

Scheduled Work Tasks
Work Task

Related Window Descriptions

Work Task/Scheduling
Scheduled Work Tasks

Procedure

  1. Go to Service and Maintenance/Work Task Management/Scheduled Work Tasks. Query for a scheduled work task record that is marked with Plan Changes (Check-box). Make sure that the work assignment status for the record is either in Assigned or Accepted.
  2. Right click on the record and select Update Plan Changes.
  3. The Work Assignment will be updated with the data from the latest scheduled plan for the activity.

Optional: Create a Scheduled Database Task for Update Plan Changes

  1. Go to Solution Manager/Background Processing/Scheduled Database Tasks. Create a new record (F5)
  2. Enter a Schedule Name.
  3. Open the List of Values in Database Task. Select the Database Task named Scheduled Plan Changes.
  4. Define when to perform the Scheduled Task
  5. Enter the ID of the scheduling dataset that the background job should be applicable for. Use % to denote that the background job will run for all Datasets.
  6. In Work Assignment Status set the status for uptil when it is allowed to update a work assignment from the background job. Applicable values are Assigned, Accepted and OnRoute.
  7. Define the Plan Change (in Minutes). If the difference between the activity allocated start of the latest plan and the work assignment is less than this value, the work assignment will not be updated to the latest scheduled plan.
  8. Save.
  9. Activate the Scheduled Database Task.