Confirm Purchase Order
Explanation
This activity is used to confirm the purchase order related to the
subcontracted work. Job
owner creates this purchase order expecting the supplier's final confirmation over
the subcontracted work, before it releases.
Prerequisites
- B2B interface, Bid for Work must be available and
accessible.
- Log in user should have the respective B2B Supplier- User connection.
- Purchase Order related to the subcontracted work must have been created
and Released.
System Effects
- Purchase Order is confirmed.
- Respective work task is set as Released.
Related Window Descriptions
N/A
Procedure
Use the following procedure to confirm purchase order, related to
subcontracted work.
- Open the
Subcontract Work Orders > Bid For Work
Lobby Page.
- Find the Lobby Section for Confirmation List.
- Click on the To be Confirmed Counter to navigate to the respective
purchase orders.
Confirm Purchase Order Lines,
- Select the Purchase Order line to be confirmed.
- Choose the Confirm button enabled at the top of the line.
- Notice the line status changes.
- Optionally set the Contractor Coordinator to coordinate the rest of
the work.
- Select the next line and proceed as above in step 2.
Confirm Purchase Order,
- Select the Purchase Order lines to be confirmed.
- Choose the Purchase Order button enabled at the top of the line.
- Choose the Confirm Order button available on the purchase order
header.
- Optionally set the Contractor Coordinator to coordinate the rest of
the work.