A SLA order template is a template which includes the service level agreement template lines defined for different work stages of the service. Scheduling data could be defined per service level agreement template line. A SLA order template can be the service level agreement between the service company and the customer to agree upon a latest start and latest finish of the service.
An active SLA order template can be connected to one or more service contract SLA lines. The SLA order template is used to auto generate a SLA order and will be connected to a work order and/or a work task.
Possible statuses on a SLA order template are Preliminary, Active, Obsolete and Cancelled.
SLA Order Template Status |
Description |
Preliminary |
This is the initial status that the order
template receives when created or the status when an Active order
template is revised. |
Active |
A SLA order template in this status can be
used in service contract SLA lines and no changes are allowed on order
template |
Obsolete |
This status indicates that the order template
has stopped being used and/or has been replaced. A SLA order template can
|
Cancelled |
A SLA order template that is in
Preliminary or Active status can be cancelled. For example, this
can be done if the order |
SLA order template lines defined for different work stages of the service. The initial SLA order template line is specified as the default and can be changed to a different line later on. These lines will be used to create SLA order lines when applicable.
On SLA order template line, Calculation Basis can be set as either Base Data or Previous Task and this indicates how the SLA Latest Start and SLA Latest Finish on a work task is calculated. (i.e. SLA order generated from the SLA order template is connected to the work task)
Base Date: SLA latest start and SLA latest finish dates are calculated based on entry date of the work task to the system.
Previous Task: SLA latest start and SLA latest finish dates on a work task is calculated based on the actual completion of the preceding work task or the actual completion of the last work task connected to the SLA order line defined on the Related Template Line No.
SLA order template schedule lines are defined per SLA order template line and a Scheduling Type is mandatory. The first line defined will be considered as the primary scheduling line and can be changed later on. These lines will be used to create SLA order schedule line when applicable.