Enter Analysis Results for Production Schedule Parts
Explanation
Use this activity to enter analysis results for one or more analyses
connected to a production schedule.
This activity allows you to record the measure quality results against the
quality test plan (Control Plan) on completion of a production schedule.
Specific quality test results for a part within a manufacturing cell are
recorded. The analysis must first be created during the production schedule
receipt process.
You can change the status of a data point to Complete. Only data
points in
complete status are considered when creating control charts or calculating capability indices.
Once the data point has this status, the results cannot be edited. You can also create a new control chart
if SPC is
activated in the control plan.
When all
data points for an analysis have been reported, you can change the status to
Confirmed.
Once an analysis has been confirmed, the results cannot be edited.
This activity contains a Security Checkpoint which can be activated by an
administrator. With an activated security checkpoint on a function you will have
to authenticate yourself again in order to fulfill the function. Additionally,
whenever a security checkpoint is successfully passed a security checkpoint log
is written, creating an audit trail of what is done.
Prerequisites
This activity has the following prerequisites:
- This activity requires analyses to have been created in the
Production
Schedule by Line,
Production Schedule by Line Part,
Production
Receipt, or
Report Point
Receipt window.
- To be able to enter analysis results, an analysis
must exist in the Planned status.
System Effects
As a result of this activity, analysis results has been
entered, completed and confirmed. Once an analysis has been confirmed, the
results cannot be edited.
- Results can be used in the creation of various IFS/Quality Management charts.
Window
Analysis
Result
Overview Production Schedule Analysis
Related Window Descriptions
Analysis Result
Production Schedule Analysis
Create Analysis
Production Schedule
Production Schedule Analyses
Procedure
To perform this activity, follow these steps:
- If you are working on previously created analyses, open the
Analysis Results window and query for the part
for which you want to enter data.
- If you just created the analyses, the system prompts you to indicate
whether you want to view the created analysis overview. If you click Yes,
the Overview Production Schedule Analysis window appears. Right-click on the line for which you want to report results and
then click Analysis Result to open the
Analysis Result window.
- If the part is serial tracked and variable or
category data type results need to be
entered, right-click on the header and click Enter Serial Numbers.
The Enter Serial Numbers dialog box is opened. Select the
Selected Serial No check boxes for the corresponding serial numbers of
the parts included in the analysis. Click OK.
- If the part is lot/batch tracked, and if the corresponding lot/batch
number has not been filled in Lot/Batch No field in the header, then
enter a value in the Lot/Batch No field. Use the List of Values to
select a suitable value.
- To print a test instruction, right-click in the header and then click Print Test Instruction. The test instruction includes all control plan
lines.
- Optionally, in the Analysis Results header, select a
filter value for the Data Point Filter field to populate the analysis
according to the selected option.
- For data points defined as variables, select the Variables tab
and enter your results in the Result field. For serial tracked parts,
the serial number also needs to be entered in the Serial No field.
Use the List of Values to select a suitable value.
If the data point has a connection to one or several tools, select a Tool
ID and Tool Instance from the List of Values in these fields.
- For data points defined as attributes, select the Attributes tab
and enter your results in the Nonconformities (c/u) and/or the
Nonconforming (np,p) fields. If the data point
has a connection to one or several tools, select a Tool ID and Tool
Instance from the List of Values in these fields.
- If the data type is categorical and Category
Entry Type is set to Single Row (visible in Detail tab),
select a category value ID for each data point. If Category Entry Type
is set to Multiple Row, enter a quantity for each category value ID
for each data point.
For serial tracked parts, the serial number needs to be entered in the
Serial No field for all parts in the sample size. Use the List of Values
to select a suitable value.
If the data point has a connection to one or several tools, select a tool ID
and tool instance from the List of Values in these fields.
- Save the changes.
- To change the status to Complete, right-click and then click Complete
Registered Results.
- To create a new control chart if SPC is activated in the control plan,
right-click on the line and click Create SPC Chart.
- To add document text to any line, right-click and click Document Text.
- To print a report of your results for any line, right-click and click Print Data Sheet.
- To confirm a single analysis, right-click in the header of the analysis
and then click Confirm Registered Results.
- When the analysis results are confirmed, the values
in the Variable Result Status, Attribute Result Status
and Category Result Status fields are updated automatically.
- To confirm multiple analyses, select one or more analysis in the
Production Schedule Analyses window, and then right-click and click
Confirm Registered
Results.