Set Baseline

Explanation

Perform this activity to create a baseline for the project. A baseline is a plan against which project execution is compared and differences are measured for the purpose of project performance analysis and control. It is possible to create any number of baselines per project, whenever it is necessary due to approved changes in scope, schedule or cost. When setting a new baseline, the Earned Value Method is selected, this will determine if the Earned Value and Scheduled Work project indicators should be calculated based on baseline values or planned values.

Prerequisites

System Effects

Each time you set a base line:

Window

Projects
Project
Project Navigator

Related Window Descriptions

Projects
Project Navigator
Project/General
Project/Project History

Procedure

From the Projects or the Project window:

  1. Open the Projects or the Project window.
  2. Populate or query for the project you need to set the base line.
  3. Right-click and then click Set Baseline. The Set Baseline dialogue box will appear. If you have populated the Projects window, select the appropriate project line and then right- click on it.
  4. Select the desired earned value method from the Earned Value Method list box.
  5. Optionally you can add a comment in the User Comment text field.
  6. Click OK.

From the Project Navigator window:

  1. Open the Project Navigator window.
  2. Populate or query for the project you need to set the baseline.
  3. Select the highest level in the project navigator. Right-click and then click Set Baseline. The Set Baseline dialogue box will appear.
  4. Select the desired earn value method from the Earned Value Method list box.
  5. Optionally you can add a comment in the User Comment text field.