Use this activity to print project pick lists. You can preview before printing. The pick list is used as a basis for picking reserved material from inventory. The pick list does not imply a physical reservation of parts.

There are five ways to generate a project pick list:

Prerequisites

 To perform this activity, the reserved quantities for the project demands should be greater than zero.

System Effects

Window

Project Navigator
Project
Projects
Delivery Projects

Related Window Descriptions

Project Navigator
Project
Projects
Delivery Projects

Procedure

  1. Select the project (or delivery project) with material reservations.
  2. Right-click and click Project Pick List.
  3. Specify the site for which you want the pick list to be generated.

Note: If you keep the Site field blank the pick list will be generated for all the sites that belong to the project.

  1. Click OK to proceed.
  2. The Report Print dialog box appears. You can choose the type of page layout or language in this dialog box.
  3. After you make desired changes, click OK to print the report directly, Cancel to abort the printout, or Preview to preview the report.
  4. If you select Preview, the report is presented for review. After reviewing it, click Print to print the report.