Create Resource Forecast Lines
Explanation
Resource forecast lines contain the estimated hours. A resource forecast may consist of a number of lines for each
resource depending on the resource criteria.
This activity explains how to add a resource forecast line to an existing
resource forecast version.
Prerequisites
- Resource Groups must be defined in the Resource
Groups window or in the Resource
Navigator/Resource Structure/Resource Groups tab.
- Capacity and cost should be defined for the
resource groups.
- Resource Criteria must be defined in the
Project/Resource
Criteria tab.
- A resource forecast version should exist.
- If the project has mandatory code parts the posting should be set up.
- Spread profiles should be defined in the Project
Spread Profile window if spreading should be done automatically by using
predefined spread profiles.
System Effects
- The resource forecast line will be created and the ETC hours will be
spread linear or nonlinear based on a spread profile.
- ETC Hours and ETC Cost will be updated for the
resource forecast line. If the cost of the resource or postings are changed
later it is possible to use the Update Cost menu option and update
the change.
Window
Project Resource Forecast
Related Window Descriptions
Project Resource Forecast
Procedure
- Open the
Project Resource Forecast window and query for the resource forecast
version for which you want to add a resource forecast line.
- Click the Forecast tab.
- Select a resource group in the resource navigator
to simplify entering a resource group to the resource forecast line.
- Create a new resource forecast line.
- Use
the List of Values to select values for the Sub Project ID field and Activity ID
field. You can use the WBS navigator to
select a required level. If you add a new line, values for what
was selected in the WBS navigator will automatically be entered on the
new line.
- In the Resource ID field, use the List of Values
(if you have not selected the relevant resource group
in step 3 above) to select a
resource which you want to use for the forecast line.
- Enter a value in either the ETC hours or EAC hours field.
Once it is saved, if
one of these estimates is the only one made on the forecast line, a value
for the remaining empty field will be calculated to be equivalent to the field with the
value.
- Optionally, you can change the default spread profile which is
automatically assigned, if you want to use another spread
profile for the spreading.
- Click Save.