Connect/Disconnect Resource Forecast

Explanation

Use this activity to connect a resource forecast to a budget/forecast version.

Prerequisites

System Effects

Window

Project Forecast

Related Window Descriptions

Project Forecast
Forecast Connection

Procedure

Use the following procedure to disconnect a resource forecast from a selected budget/forecast version:

  1. Open the Project Forecast window, query for the project budget/forecast version for which you want to disconnect the resource forecast. 
  2. Right click on the window, click the Forecast Connection menu option. The Forecast Connection dialog box will open.
  3. Select the Resource Forecast tab
  4. Select the required row and click Remove.
  5. Click OK.

Use the following procedure to connect a resource forecast to the selected budget/forecast version:

  1. Open the Project Forecast window, query for the project budget/forecast version for which you want to connect a resource forecast.
  2. Right click on the window, click Forecast Connection. The dialog box opens up.
  3. Select the Resource Forecast tab.
  4. Press New to enter a new line.
  5. In the Resource Forecast Version ID field, use the List button to select an existing set of previously created resource forecasts that you want to connect to the selected budget/forecast version. Alternatively, it is also possible to use Select Batch to select more than one resource forecast.
    Note. It is not possible to connect a resource forecast if the project has an active budget using net change budget control
  6. Click OK.

Use the following procedure to update a resource forecast from a selected budget/forecast version:

  1. Open the Project Forecast Info window, query for the project budget/forecast version for which you want to update the resource forecast. 
  2. Right click on the window, and click Forecast Connection. The dialog box opens up.
  3. Select a row and click Update.
  4. Click OK.