Complete Activity

Explanation

Perform this activity to set the selected project activity to the Completed status. Completing an activity means that no new work can be started, but the work you have already started can be completed. Once an activity is in the Completed status, it can be promoted to Closed status or be reopened into Released status.

Prerequisites

System Effects

Window

Activities
Project Navigator/Activity List
Project Navigator/Activity

Related Window Descriptions

Activities
Project Navigator/Activity List
Project Navigator/Activity

Procedure

  1. Open the Activities window and query for the required activity that needs to be completed.
  2. Right-click and click Complete in the menu.