Assign Resource to Activity
Explanation
Perform this activity to add a resource to an activity. The main purpose of
this is to control who will work on a certain activity and how much work is to
be done, with more detail. The values given here will be used for performing an
approximate capacity planning across one or more projects.
Several
resources can assign to one activity. It is important that the resources
connected have cost and capacity defined for the right period according to the
project. The resource cost and capacity to use is defined by the early start and
finish dates of the activity. The cost and hours for the resources will be
reported to the project according to the posting control setup.
It is possible to add a resource to the planning also when project level or
sub-project level is selected. But in those cases, sub project ID and/or
activity ID need to be specified since the project resource planning is always
done on activity level.
Same resource ID can assign on several lines by using the resource criteria.
Prerequisites
- Resource groups with capacity and cost should be defined
in the Resource
Groups window or in the Resource
Navigator/Resource Structure tab.
- Resource criteria should be defined to be able to use another level
of planning other than only resource.
System Effects
- The activity will be included in the rough capacity planning.
- Planned hours and planned cost will be updated for the resource line. If
the cost of the resource or postings are changed later it is possible to use
the Update Cost menu option and update the change.
Window
Project Navigator/Resource
Activity/Resource/Resource
Planning
Activity Resources
Related Window Descriptions
Project Navigator/Resource
Activity/Resource/Resource Planning
Activity
Resources
Procedure
- Open the Project
Navigator window and select the appropriate activity from the graphical
structure navigator.
- Go to the Resource tab and click on
the Resource Planning
tab.
- Select a resource group in the resource navigator
to simplify the entry of resource group in the resource planning line.
- Create a new record.
- Select a Resource ID from the List of Values if
relevant resource group was not selected in step 3 above.
- Appropriate criteria can be selected if resource criteria have set up.
It's possible to use % for all.
- Required duration type can select in the Duration Type
column if any interface takes place with Primavera Project Planner.
- Enter a value in the Planned Hours column.
- Enter a text in the Note field if needed.
- Save the record.
Note that the above procedure can also be done in the
Activity/Resource/Resource Planning tab.