Explanation
Use this activity to run project MRP for parts, by using a project deliverable
structure.
Prerequisites
- An approved project deliverable structure with project defaults and part
information, must have been created.
- Parts should have been defined with the supply option Project MRP.
- Deliverable items must be approved.
- Project activity must be released.
System Effects
As a result of this activity, selective project MRP will be performed and
supplies will be planned for the inventory part(s).
Window
Project Deliverables Navigator
Project Deliverables Definition
Project Navigator
Project
Activity
Related Window Descriptions
Project Deliverables
Navigator/Materials/Material Plans
Project Deliverables Navigator/Project MRP Plan/General
Procedure
The project MRP for part option is available in the following places:
- Project Deliverables Navigator/Project MRP Plan/General
tab
- Project Deliverables Navigator/Materials/Material
Plans
tab
- Project Deliverables Definition/Demand/Material
Plans
tab
- Project/Demand/Project Deliverables Demand tab
- Project Navigator/Demand/Material Plans tab
- Activity/Supply/Demand/Material Plans tab
- Open the one of the above places and where the demand is defined with
supply option Project MRP.
- Right-click and click Perform
Project MRP for Part.
The project MRP can now be further processed, as described here:
Make to Stock
Planning