Perform MRP for Part
Explanation
Use this activity to run project MRP for parts in a project deliverable
structure.
Prerequisites
- An approved project deliverable structure with project defaults and part
information, must have been created.
- Parts should have been defined with the supply option MRP.
- Deliverable items must be approved.
- Project activity must be released.
System Effects
As a result of this activity, selective MRP will be performed and
supplies will be planned for the inventory part(s).
Window
Project
Deliverables Navigator
Related Window Descriptions
Project Deliverables
Navigator/Materials/Material Plans
Project Deliverables Navigator/MRP Plan/General
Procedure
- Open the Project Deliverables Navigator window and populate it
with values.
- Expand the structure and navigate to the MRP Plan of the
part you wish to perform MRP for part.
- In General tab, right-click and select Perform
MRP for Part option.
- The Perform MRP for Part dialog box will be opened
with part number(s) and site already selected.
- Select the date on which you want the selective project MRP to be
executed. The site date is used by default.
- If you want to stop the project MRP process when an error occurs, you
can select the Stop PMRP on Error check box.
- To add one day lead-time back-off to planned receipts, select the Add
1 Day Lead Time check box.
- If you want to create messages for phantom part dependent demands,
select Phantom Part Dependent Demand Message check box.
- To start the MRP process immediately after project MRP is completed,
click the Start MRP Once PMRP is Completed check box.
- If you want the MRP process to create safety stock replenishment orders
on the MRP run date, select the Plan Safety Stock Receipt on MRP Run Date
check box. If it is not selected, safety stock replenishment orders will be
created on the event date itself.
- If the Run Integrated with CRP check box is selected, CRP
backward scheduling logic will be used to schedule shop order requisitions
generated from the process. As a result, the start date of the
requisitions/receipts generated will be more accurate.
MRP can now be further processed, as described here:
Make to Stock
Planning