Perform MRP for Part

Explanation

Use this activity to run project MRP for parts in a project deliverable structure.

Prerequisites

System Effects

As a result of this activity, selective MRP will be performed and supplies will be planned for the inventory part(s).

Window

Project Deliverables Navigator

Related Window Descriptions

Project Deliverables Navigator/Materials/Material Plans
Project Deliverables Navigator/MRP Plan/General

Procedure

  1. Open the Project Deliverables Navigator window and populate it with values.
  2. Expand the structure and navigate to the MRP Plan of the part you wish to perform MRP for part.
  3. In General tab, right-click and select Perform MRP for Part option.
  4. The Perform MRP for Part dialog box will be opened with part number(s) and site already selected.
  5. Select the date on which you want the selective project MRP to be executed. The site date is used by default.
  6. If you want to stop the project MRP process when an error occurs, you can select the Stop PMRP on Error check box.
  7. To add one day lead-time back-off to planned receipts, select the Add 1 Day Lead Time check box.
  8. If you want to create messages for phantom part dependent demands, select Phantom Part Dependent Demand Message check box.
  9. To start the MRP process immediately after project MRP is completed, click the Start MRP Once PMRP is Completed check box.
  10. If you want the MRP process to create safety stock replenishment orders on the MRP run date, select the Plan Safety Stock Receipt on MRP Run Date check box. If it is not selected, safety stock replenishment orders will be created on the event date itself.
  11. If the Run Integrated with CRP check box is selected, CRP backward scheduling logic will be used to schedule shop order requisitions generated from the process. As a result, the start date of the requisitions/receipts generated will be more accurate.

MRP can now be further processed, as described here: Make to Stock Planning