Enter Plant on Project Deliverable Definition

Explanation

Use this activity to enter a plant on project deliverables definition.

Prerequisites

Object property COPY_TO_MAINTANANCE must be set to NO, as described here: Set Object Property for enabling the Copy to Equipment or Copy to Asset Design.

A standard and plant must have been created in Asset Design, as described here: Define Standard and Define Plant.

Note : IEE must be refreshed/restarted after setting object property to NO

System Effects

Classes can be entered on project deliverable items, once a value for plant has been defined on the project deliverable definition, as described here: Enter Class on Project Deliverable Definition.

Window

Project Deliverables Definition

Related Window Descriptions

Project Deliverables Definition

Procedure

  1. Open the Project Deliverables Definition window and search for a record.
  2. Enter a plant name or select from List of Values.
  3. Save your changes.