Copy Operations and Guidelines from Template
Explanation
Use this activity to copy operations and guidelines from a predefined
template.
Prerequisites
- A project deliverable item should exist, as described here:
Create Basic Structure.
- An inventory part of any manufactured type must have been defined on
project deliverable item, as described here:
Create Detailed Structure.
- The value for Supply Option, on the material in Material
Requirements
tab, should be set to Shop Order. Reviewed supply option, as described
here: Review Supply Option.
System Effects
Operation and guidelines are copied to project deliverable item.
Window
Project
Deliverables Navigator
Related Window Descriptions
Project Deliverables
Navigator/General
Project Deliverables
Navigator/Components
Project Deliverables
Navigator/Materials/Material Requirements
Project Deliverables Navigator/Navigation Items
Procedure
- Open the Project Deliverables Navigator window and populate it with
values.
- Open the General tab, Components tab,
Materials/Material Requirements or
Navigation Items tab.
- Select Items with Use Project Operations check box is checked.
- Right-click and then click Project Operations.
- This opens Project Operations window.
- Right-click and select Copy Operations option.
- This opens Copy Operations dialog and where Operations
and Work Guidelines can be copied from a Template.
- Select Routing Template from the Copy From drop down list
and enter all required information using List of Values.
- Check Copy Work Guideline check box to copy Work Guidelines
from Template.
- Save changes.