Explanation
The progress' begin date, lead time,
expected approval date, stage
amount, last stage payment line, etc. may change for a milestone/stage
payment. If this is the case, it is possible
to update the milestone/stage payment line. It is also possible to remove a milestone/stage
payment.
Prerequisites
- A milestone/stage payment must have been entered and saved for a purchase order
line.
- The milestone/stage payment line must be in state
Released.
System Effects
A milestone/stage payment will be either updated or removed.
Window
Purchase Order
Purchase Order Lines
Milestone/Stage Payment for Purchase Order Lines
Related Window Descriptions
Milestone/Stage Payment - Purchase Order
Purchase Order
Purchase Order/Part Order Lines
Purchase Order/No Part Order Lines
Purchase Order Lines
Milestone/Stage
Payment for
Purchase Order Lines
Procedure
Update a milestone/stage payment line:
- Open the Purchase Order window and query for the appropriate order.
- On the
Purchase
Order/Part Order Lines tab, right-click on the relevant order
line, point to Order Line Details and then click Milestone/Stage
Payment; or on the
Purchase Order/No Part Order Lines
tab, right-click on the relevant order line, and then click Milestone/Stage Payment.
Note: This activity can also be done in the
Purchase Order Lines and
Milestone/Stage Payment for Purchase Order Lines windows.
- On the dialog box that appears, change
the progress, begin date, lead time, expected
approval date, stage
amount, last stage payment line, etc. for a
milestone/stage payment line. If the begin date is changed,
the expected completion
date
is recalculated according to the lead time. If the
lead time is changed, the expected
completion date is recalculated according to the new lead time.
- Save the updated milestone/stage payment line.
Remove a milestone/stage payment line:
- Open the Purchase Order window and query for the appropriate order.
- On the
Purchase
Order/Part Order Lines tab, right-click on the relevant order
line, point to Order Line Details and then click Milestone/Stage
Payment. On the
Purchase Order/No Part Order Lines
tab, right-click on the relevant order line, and then click Milestone/Stage Payment.
Note: This activity can also be done in the
Purchase Order Lines and
Milestone/Stage Payment for Purchase Order Lines windows.
- Select the line(s) that need to be removed.
- Click Remove on the tool bar.
- Save the modified line(s) and the milestone/stage
payment line(s) will be removed.