Study MRP Part Information by Periodic Template
Explanation
Use this activity to view
information about planned receipts/deliveries and gross requirements for parts by using periods specified by a template. It is possible to
recalculate the details for the desired template from this tab.
Prerequisites
The material requirements calculation must have been performed for the part. The period
template must have been defined.
System Effects
As a result of this activity, the system displays gross demands for a part using
periods specified by a template.
Window
MRP Part Information
Related Window Descriptions
MRP Part Information
MRP Part Information/Gross Requirements
by Template
Recalculate Period Template
Select Period Template
Procedure
- Open the MRP Part Information
window.
- Search for the part for which you want to study the specified
information.
- Click the
Gross Requirements by Template tab to view gross
requirements for the part calculated by MRP using periods
specified by a template. If a default template exists for the
site with which the selected part is associated, it is used to display the gross
requirements information.
- To change the period template, right-click the header of the
Gross
Requirements by Template tab and then select Select Period Template.
The Select Period Template
dialog box is opened. Select the period template in the Template ID
field. Click List to select from available period templates. Click OK.
- To update the period template details, right-click on the header of the
Gross Requirements by Template
tab and then select Recalculate Period Template. Select the begin date for the first period in the Period 1
Begin Date field and select the calendar in the Calendar ID
field. Click List
to select from available calendars.
- Click OK.