Propagate Quantity Downstream

Explanation

This activity is used to propagate quantities downstream in a DOP structure (to parent levels). The quantities on higher levels in the DOP structure will change with respect to the quantity on the DOP order on which you perform the command.

Prerequisites

This activity requires that a parent DOP order exists.

System Effects

As a result of this activity:

Window

DOP Header
DOP Order

DOP Orders

Related Window Descriptions

DOP Header
DOP Header/Structure
DOP Header/Tree Structure
DOP Order
DOP Order/Detail
DOP Order/Tree Structure

DOP Orders

Procedure

  1. Select the DOP Order from which to start a downstream propagation of quantities.
  2. Right-click and point to Propagate Date/Quantity, then click Propagate Quantity Downstream.

From the graphical object structure (DOP Order/Tree Structure or DOP Header/DOP Structure):

  1. Select the DOP Order from which to start a downstream propagation of quantities.
  2. Right-click on the selected DOP Order, point to Propagate Date/Quantity, and then click Propagate Quantity Downstream.

From the DOP Orders window:

  1. The one or several DOP orders from which to start a downstream propagation of dates. Note that the DOP orders must belong to different DOP ID's.
  2. Right-click and point to Propagate Date/Quantity, then click Propagate Quantity Downstream.