Net All (DOP Header)

Explanation

Use this activity to manually initiate the automatic netting processes for the entire DOP structure. The alternative is to automatically initiate this netting process upon release of the DOP header. This requires certain basic data settings for DOP. Refer to the activity Set DOP Netting Method.   

You can perform re-netting when either the quantity or the structure is changed after the release; you can re-net after canceling netting relations.

Netting is performed in the following sequence:

For DOP orders where the DOP header is connected to a project, and where the Create Pegged option is set to Pegged Orders, netting is allowed only from the project inventory. If the Create Pegged option is set to No Pegged Orders, netting is allowed only from standard inventory. 

For project connected DOP orders, netting is performed in the following sequence:

Prerequisites

This activity requires that:

System Effects

As a result of this activity:

Window

DOP Header

Related Window Descriptions

DOP Header

Procedure

  1. Open the DOP Header window.
  2. Select the DOP header that you want to net.
  3. Right-click on the header area and then click Net All.
  4. A message appears to indicate that the system is about to net all DOP orders, click OK to confirm.