Net DOP Order

Explanation

Use this activity to manually initiate the automatic netting processes for a specific DOP order. You can also automatically initiate this netting process upon release of the individual DOP order. This requires certain basic data settings for DOP. Refer to the activity Set DOP Netting Method.

It is also possible to perform re-netting when either the quantity or the structure is changed after the release; you can re-net after canceling netting relations.

Netting is performed in the following sequence:

For DOP orders where the DOP header is connected to a project, and where the Create Pegged option is set to Pegged Orders, netting is allowed only from the project inventory. If the Create Pegged option is set to No Pegged Orders, netting is allowed only from standard inventory. 

For project connected DOP orders, netting is performed in the following sequence:

Prerequisites

This activity requires that:

System Effects

As a result of this activity:

Window

DOP Header
DOP Order

Related Window Descriptions

DOP Header
DOP Header/Structure
DOP Order
DOP Order/Components
DOP Orders

Procedure

  1. Search for the DOP order to net.
  2. Right-click, point to Net and then click Order.
  3. A message appears inquiring whether you want to net the DOP order(s), click Yes to confirm.