Create Pegged Order
Explanation
This activity is used to create a pegged order for a specific DOP order. This
functionality is used to create supply for a DOP order where the demand has
increased, or the supply has decreased after the DOP order has been released.
Prerequisites
This activity requires that the DOP order is in Released state and
that the DOP order quantity has increased, or the supply order quantity has decreased after release.
System Effects
As a result of this activity:
- A new pegged order is created for the DOP order. If the part has a scrap
factor defined, the shop/purchase order will be created with a quantity
higher than the quantity required by the DOP order to cover for the planned
scrap.
- If the DOP order is project specific the pegged order
created will be tagged with Project ID and Activity Sequence.
Window
DOP Header
DOP Order
Related Window Descriptions
DOP Header
DOP Header/Structure
DOP Order
DOP Order/Detail
Procedure
- Select the DOP Order you want to create a pegged order for.
- Right-click and then click Create Pegged Order.