Use this function to copy a default structure from BOM. The valid structure revision and alternative due to the date or serial numbers reserved is used.
This activity has the following prerequisites:
As a result of this activity:
If the Structure Depth list in the DOP Header/Detail window is set to Full Level, DOP orders will be created for all levels in the BOM, and set the Create Pegged to Pegged Orders for all the generated DOP orders.
If the Structure Depth list in the DOP Header/Detail window is set to DOP Parts, DOP orders will be created for the parts with the Default Supply Type set to DOP in the Inventory Part/Planning Data/General window, and the level below it in the BOM. The Create Pegged will be set to Pegged Orders for all parts with the default supply type set to DOP.
If the DOP header is project specific, DOP Orders that are created in the structure will be tagged with Project ID and Activity Sequence.