ERMPL
Project Navigator/Demand/ERMPL
Project/Demand/ERMPL
Activity/Demand/ERMPL
Project Product/Demand/ERMPL (Project Delivery)

[About Project Management in IFS/Asset Design] [About Material Handling] [To Asset Procurement]

Usage

Use this window or tab to view a summary of the registered additional part demands of a design object connected to a project. Additional parts that are not connected with part numbers will not be created as ERMPL records. However, once an additional part receives a part number it is possible to update the ERMPL record with this additional part demand by refreshing the ERMPL on the additional part's design object/project connection.

If the Design Obj. CE Updated check box has been selected, it means that any changes made to the planned cost/cost elements of the related parts in this window/tab will be updated on the design object.

Right-click on the relevant part line and select the Cost Elements option to make changes to the part planned cost. Updating can be done through a right mouse button menu option on the ERMPL window or on the ERMPL tabs for project related windows. You can also choose to manage the reservation and issue of parts as well as view the connected purchase requisition, purchase order, inventory and purchase part details from this window/tab. Any planned cost changes to the parts will be updated back to the Connections tab of the connected project activity.

Activity Diagrams

Handle Material Demand

Activities

Add/Modify Planned Cost Details on ERMPL Demand Part
Update Planned Cost from Supplier Price
Update Planned Cost from Latest Purchase Order
Reserve Inventory to Project
Issue from Inventory to Project

UnIssue to Inventory from Project
Update Design Object Planned Cost from ERMPL