Activate Operational Plan
Explanation
Use this activity to activate the operational plan. If IFS/Maintenance
Planning Board (MPB) is used, it is mandatory to load active operational plans
which is connected with equipment object structure and if there are work orders
and PM occurrences to be scheduled for the Equipment objects in the object
structure and will be used to derive the object accessibility when scheduling
tasks/operations if applicable.
An operational plan can be viewed in maintenance planning board even if it
is in under preparation or active statuses if needed.
Prerequisites
To perform this activity:
- An operational plan in UnderPreparation status should exist in the
system.
System Effects
- As a result of this activity, operational plan become active.
- If IFS/Maintenance Planning Board (MPB) is used,
operational plan can be used as a guidance or to derive the object accessibility for
scheduling
tasks/operations in MPB if applicable.
Window
Operational Plan
Related Window Descriptions
Operational Plan
Procedure
- Open the Operational Plan
window.
- Query
(F3) for an Operational Plan that are in the status UnderPreparation.
- Right click in the window and select Set Active.