Update Level One Parts

Explanation

This activity is used to update the roll flag, the time fence and the family type of the level one parts, that belong to the planning structure of the level 0 part.

Prerequisites

To perform this activity, the level 0 part should be defined in the MS Level 0 Part window and the MS Level 1 Part window or the respective level 1 parts are already created using the Disaggregate Level 0 to Level 1 window.

System Effects

As a result of this activity, the roll flag, time fence and the family type will be updated from level 0 to level 1.

Window

MS Level 0 Part

Related Window Descriptions

MS Level 0 Part

Procedure

  1. Open the MS Level 0 Part window.
  2. Search for the required part. To search for project master scheduled parts, use the project PNG.
  3. Change the required data.
  4. Right-click and then click Update Level 1 Parts.
  5. The required changes you made in this window, will be updated in the MS Level 1 Part window.