Enter Master Schedule Level 0 Forecast
Explanation
This activity is used to enter forecasts for level 0 parts.
Prerequisites
This activity requires that the part must have been registered as a level 0 part before
you can enter the forecast.
System Effects
As a result of this activity, the system automatically transfers the forecast you enter
on level 0 to level 1 when the disaggregation process is performed.
Window
MS Level
0 Part
Related Window Descriptions
MS Level 0 Part
MS Level 0 Part/Register Forecast
Procedure
- Search for the relevant MS level 0 part and click the
Register Forecast
tab.
- In the MS Set list, select the master schedule set for which you want to
enter forecasts. If the required MS set is not available in the list, create
a new record and use the List of Values to select from available MS sets and
Save.
- Create a new record in the table below.
- In the Forecast Date field, enter the date when the forecast will be valid. The system
determines if the date is within or outside of the time limit.
- Enter the forecast for the part in the Forecast field.
- Repeat steps 3-5 for each forecast you want to register.
- Save the information. When you save the forecast, the period is displayed.