Define Master Schedule Level 1 Part
Explanation
Use this activity to register an inventory part as master scheduling level 1
part.
Prerequisites
An inventory part with planning method other than B, C, K, T, O H or N must
exist.
System Effects
As a result of this activity, the part is registered as a master schedule
level 1 part.
Window
MS Level 1 Part
Related Window Descriptions
MS Level 1 Part
Procedure
- Open the MS Level 1 Part
window.
- Create a new record.
- In the Part No field, enter the part number for the part you want to register
as a MS level 1 part or use the List of Values to select from available
parts.
- Enter a value in the Demand field.
- Enter a value in the Planning field.
- If you want to plan a part which is project
connected, enter a value in the Project PNG and Activity ID fields.
- Save.