Report Scrap
Explanation
Use this activity to report scrapping from manufacturing.
If the operation is connected to a component line and that component line is
not issued prior to reporting the operations, it will be issued using the backflush
feature. If any of the components being issued by the backflush feature is catch
unit enabled, the full quantity in the inventory part location must be issued to
complete this activity. The operation must be connected to the material line.
If only a part of the quantity in an inventory location is issued, you will have
to manually issue the components before reporting scrap.
Prerequisites
This operation requires that the shop order has at least Released status.
The operation cannot have Closed status.
If the Over Reporting list is set to Not Allowed on the
Inventory Part/Manufacturing tab, the sum of the reported quantity
complete and scrap must be equal to, or less than the planned operation quantity
plus the defined over report tolerance.
System Effects
As a result of this activity, the system reports scrap for an operation. The
remaining quantity of the following operation decreases by the scrapped quantity.
If the operation the scrap was reported on has the Increased Lot Size on
Scrap check box selected, the following operation will not decrease the
remaining quantity by the scrapped quantity.
A Work In Process (WIP) transaction is created.
Reporting scrap will in some cases affect manual peggings. When reporting scrap
on a shop order operation where the parent part has a manual supply pegging to a
demand, a check is performed to see if the quantity to receive is less than quantity
pegged to the demand. If quantity to receive after scrap is less than quantity pegged
you will be notified to manually adjust the peggings before the scrap can be performed.
If Buffered Operations Reporting is enabled and the Adjust Schedule
Due To Shop Floor Reporting check box in the Scheduling
Basic Data/Shop Order Scheduling/Scheduling Server tab has been selected,
at the next execution of buffered operation reporting the scheduling server will
adjust the operation time due to remaining quantity and:
- if Prioritize Reported Operation was chosen - the reported operation
is given priority and scheduled as close as possible to now time.
- if Keep Scheduled Operation Sequence was chosen - the schedule will
be updated without altering the previous schedule sequence. Subsequent operations
in the same order structure will move closer to the reported operation in order
to fill any capacity gaps which occur immediately after the reported operation.
Window
Report Shop
Order Operations
Report
Work Center Operations
Shop Floor
Workbench
Shop Floor Reports
Time Clock
Related Window Descriptions
Report Scrap
Report Shop Order Operations/Internal Operations
Report Shop Order Operations
Report Work Center Operations/Internal Operations
Shop Floor Workbench
Shop Floor Workbench/Reports
Shop Floor Reports
Add Operation Result
Time Clock
Time Clock Data Input Dialog
Procedure
- Select the operation for which you want to report scrapping.
- Right-click and then click Report Scrap, the Report Scrap
dialog box appears.
- Enter the quantity of the scrapped parts in the Scrap
Qty to Report field. If you want to enter the quantity to report in an
alternative unit of measure, click the Input UoM option.
- For catch unit enabled parts, optionally enter the catch quantity in the Scrap Catch Qty
to Report field.
- Enter the reason for scrapping in the Scrap Reason field.
Use the List of Values to select from available scrapping reason codes.
- Optionally, enter additional information related to the scrapping event
in the Notes field.
- Click OK.
To report scrap using the Shop Floor Workbench:
- Open the Shop Floor Workbench
window and click Refresh.
- The details of the operations will be displayed according to the filter
that is being used.
- Select the operation line for which you wish to report scrap.
- Click Report Scrap to open the
Report Scrap
dialog box.
- Select Part Scrap option and the
Report Scrap
dialog box appears.
- Enter the quantity of the scrapped parts in the Scrap
Qty to Report field. If you want to enter the quantity to report in an
alternative unit of measure, click the Input UoM option.
- For catch unit enabled parts, optionally enter the catch quantity
scrapped in the Scrap Catch Qty to Report field.
- Enter the reason for scrapping in the Scrap Reason field.
Use the List of Values to select from available scrapping reason codes.
- Optionally, enter additional information related to the scrapping event
in the Notes field.
- Click OK.
To report scrap using the Add Operation Result :
- In the Shop Floor Workbench/Reports tab or Shop
Floor Reports window, use right
mouse button menu and click the Add Operation Results option to open
the dialog box.
- In the Operation ID field, use list of value to choose which operation
to register the reports on.
- In the Date field, enter the date which on the reports should be
applied.
- In the Qty Scrapped field enter the quantity to report as scrap.
- For catch unit enabled parts, optionally enter the catch quantity
scrapped in the Catch Qty Scrapped field.
- Enter the reason for scrapping in the Reported Scrap Reason field.
Use List to select from available scrapping reason codes.
- Optionally, enter additional information related to the scrapping event
in the Notes field.
- Click OK.
To report scrap using Time Clock :
- Click the Report Scrap button in Time
Clock.
- Enter the Site to report on.
- Enter the Employee ID or the Team.
- Enter the Operation ID you want to report
scrap for.
- In the Scrapped Qty field enter the quantity to report as scrap.
- Enter the reason for scrapping in the Scrap Reason field.
Use List to select from available scrapping reason codes.
- If you want to close the operation, select Yes
in Close Operation.
- Click OK.
Note: Depending on the Time Clock
configuration, some of these fields may be automatically filled with default
data and thereby the fields may be disabled or unavailable for editing.