Explanation

When a project connected shop order is created through a project miscellaneous demand, a customer order or a manual connection, the material list is always copied from manufacturing standards. If the shop order is connected to a project activity, it should be possible to issue material from either project inventory or the standard inventory. The Redefine Supply Code option for the components will change the supply code between invent order (where the material will be issued from standard inventory) and project inventory or project (where the material will be issued from project inventory).

Both project and project inventory supply codes will reserve and issue material from the relevant project inventory and behave almost the same. The only difference between them is that the project inventory type components are planned by material planning tools like PMRP, while the project type components are not.

Prerequisites

System Effects

When a shop order is created from a project miscellaneous demand with the Shop Order supply option and the miscellaneous demand component method of the project is Manually Planned.

else,

Window

Shop Order
Shop Order Materials

Related Window Descriptions

Shop Order/Materials
Shop Order Materials

Procedure

  1. Open the Shop Order/Materials or Shop Order Materials window and search for the record for which you want to redefine the supply code.
  2. Select the component material line/lines for which you wish to redefine the supply code. Right-click and then click Redefine Supply Code.