Change Work Center

Explanation

Use this activity to re-plan the operation to another work center.

Prerequisites

An active, internal work center must exist on the same site.

System Effects

As a result of this activity the operation is rescheduled on the new work center.

Window

Shop Floor Workbench

Related Window Descriptions

Change Work Center or Resource

Procedure

  1. Open the Shop Floor Workbench window. If Reporting Mode has been set to Employee Reporting on the used site an employee or team must have been entered in the Enter As dialog box.
  2. Click Refresh. The operations will be displayed according to the filter that is being used.
  3. Select the operation line for which you want to change the work center and click the Change WC option, or right-click and select the corresponding option.
  4. In the New Work Center field, use List of Values to select the work center on which you plan to execute the operation.
  5. Click OK.