Change Lot Size

Explanation

Use this activity to change the total manufactured quantity.

When the lot size of the shop order pegged to a DOP order is changed, a message appears inquiring whether or not to automatically update the quantity for the DOP order. If the DOP order is not updated, an alarm is created for the quantity mismatch between the shop order and DOP order. A quantity shortage alarm may be resolved by either creating a new pegged order or by netting.

Prerequisites

System Effects

As a result of this activity:

Note: However in the following situations, the scheduled start time is changed:

Window

Shop Order
Shop Orders

Production Line Management

Related Window Descriptions

Shop Order
Shop Orders
Production Line Management
Production Line Management/Shop Orders

Procedure

  1. Open the Shop Order, Shop Orders or Production Line Management/Shop Orders window.
  2. Search for the shop order.
  3. In the Lot Size field, change the quantity to be manufactured.
  4. Click Save.