Explanation

Use this activity to unschedule a Scheduled resource break. The status of the break changes to Unscheduled. A resource break in Unscheduled state has no effect on the shop order schedule. Resource breaks are taken into account only when the orders are scheduled using Constraint Based Scheduling (CBS), not when using the Shop Order Infinite Scheduler.

Prerequisites

A resource break in Scheduled state must exist.

System Effects

As a result of this activity,

Window

Resource Break

Related Window Descriptions

Resource Break
Resource Breaks

Procedure

  1. Populate the window.
  2. Select the resource break(s) you want to unschedule.
  3. Right-click and then click Unschedule. The status of the selected break(s) changes to Unscheduled.