Use this activity to confirm a resource break which is in Proposed state. The status of the break changes to Scheduled. A Scheduled break is taken into account when orders are scheduled using Constraint Based Scheduling (CBS), not when using the Shop Order Infinite Scheduler.
As a result of this activity the status of the resource break changes from Proposed to Scheduled. However, before it makes this change, the system checks to see if the break overlaps with any operations or breaks which are in Released state. If it does, an error message appears and the activity is canceled. If the break does not overlap with any existing operations or breaks which are in Released state, then all operations that are simultaneous with and downstream from the start of the break are rescheduled.
Resource Break
Resource Breaks