Assign Plot Setting and Sorting Options for the Scenario
Explanation
Use this activity to assign plot setting and sorting options for the objects in a selected user defined scenario or pre-defined scenario.
Prerequisites
This activity requires that at least one user defined scenario is defined in order to assign plot settings and sort orders.
System Effects
Once a plot setting is assigned to a scenario, that plot setting will be used when the scenario is plotted on the Gantt Chart.
If sorting options are defined for a scenario, objects in the scenario are sorted based on the sort criteria once plotted.
Window
Scheduling Client
Simulation Client
Advanced Planning Board
Maintenance Planning Board
Maintenance Planning Board for Planning Network
Related Window Descriptions
Scheduling Client
Simulation Client
Advanced Planning Board
Maintenance Planning Board
Maintenance Planning Board for Planning Network
Procedure
- Right-click on a required pre-defined scenario or user defined scenario.
- On the Show contents Tab, select preferred plot setting for the selected scenario using the
Assigned Plot Setting list.
Note: All the plot settings that are defined in Tools > Setting > Plot settings will be displayed in the Assigned Plot Setting list.
- Click New to define the first sort criteria. The List of Values window opens.
- From the list of values displayed, select the attribute which you prefer to use as the first sort criteria.
Note: If there is more than one type of object in a user defined scenario, then attributes that are common to all objects will be available to select
as the sort criteria when sorting (e.g. if
a scenario consists of a few shop orders and a few resource breaks, then only 4 attributes i.e,
Need Date, EPST, Name and Class Name are available to be used as
the sort criteria).
- Select the Sort Type as Ascending or Descending for the first sort
criteria. The objects in the scenario will be sorted accordingly.
- Repeat steps 3, 4 and 5 any number of times to define the next sort criteria.