Analyze Machine Load Chart
Explanation
This activity is used to analyze the machine load in relation to the
capacity. Load is represented with bars per day, or week and capacity with a
line.
To populate the chart, click the magnifying glass and search either for
relevant shop orders, or work centers/time period depending on the page used.
When searching for shop orders, chart will show all load for the relevant work
center resources and dates.
The chart can be configured using below settings:
- Group By - Controls how the bar segments should be
divided.
- Color By - Controls the color of the bar segments. Only
available when group by has been set to Operation.
- Load Source - Controls what different types of load
that should be considered.
- Capacity Type - Controls whether the capacity line should
consider the work center utilization or not.
- Load Dates - Controls whether load should be shown only
for the dates on
which the searched data have load, or all dates within the searched data
interval.
- Aggregate By - Controls whether the X-axis should show
load and capacity per day, or per week.
- Show Only Load Dates - Controls whether the X-axis
should show only dates with visible load, or include also dates without visible
load. Note that if Date Selection has been set to
Dates, load may exists on dates even if the load is not visible in
the chart as it appears on a date where the search result
have no load.
When grouping / coloring by load sources, the below classification is used:
Load Source |
Explanation |
Planned |
Load from a planned shop order. |
Released |
Load from a released shop order. |
Started |
Load from a started shop order. |
Parked |
Load from a parked shop order. |
Maintenance |
Load from a maintenance work task. Note that below
must be fulfilled to view maintenance load from this chart:
- The task should be connected to an object which represents a work center
resource.
- The operational status type on the task should be Obstructive.
- Planned start and finish date on the task has to be defined.
- The task status should be Under Preparation,
Prepared, Released or Started.
- The execution time (planned start/finish) needs to be defined on the
task.
|
DOP |
Load from an unreleased DOP order. |
Requisitioned |
Load from a shop order requisition. |
Master Schedule |
Load from a proposed master production schedule. |
Production Schedule |
Load from a production schedule. |
Promised |
Load from a capability check created interim order
scheduled using IFS APB/CBS. |
Resource Break |
Load from a resource break scheduled using IFS
APB/CBS. |
To limit the contents of this chart based on a
selection made in another chart, open the settings dialog by clicking the
gearwheel icon and select to filter from any of below charts:
- Material Availability Summary - Chart is filtered
on the shop order(s) of the selected availability category(s). I.e. only
date interval and work centers connected to any operation on these shop
orders will be considered.
- Machine Availability Summary - Chart is filtered
on the selected work center resource(s), work center(s), department(s) or
production line(s). I.e. Load and capacity will only be shown for the
selected items.
This activity can be performed from IFS Aurena client only.
Prerequisites
- The machine capacity must have
been calculated for the site using Calculate Work Center Resource Capacity
dialog box.
- To show loads from sources other then shop order, the capacity
requirements planning must be performed for the site using Perform CRP
dialog box
System Effects