Manage PM Program Revision
Explanation
Use this activity to create a new PM program revision from an existing
revision.
A PM program with status Preliminary can be updated but once this
status is changed to Active, the PM program is locked from editing. When
a change is required, a new PM program revision has to be created.
New revisions can be created from PM program revisions in Active and
Obsolete statuses if there is no PM program revision currently in the
Preliminary status.
Prerequisites
- A PM program revision in Active or Obsolete status should
exist in the system, revision control should be enabled and a PM program
revision in Preliminary status should not exist.
System Effects
- A new PM program revision will be created with status Preliminary, including
the connections to work task templates (if applicable).
- The new revision will receive the Preliminary
status.
Window
PM Program
Related Window Descriptions
PM Program
Create New Revision for PM Program
Procedure
- Open the
PM Program window,
and query for the PM program for which you want to create the revision.
(Alternatively
you can directly query for the revision itself.)
- Right-click on the header of the window and then click Create
New Revision. The Create New Revision for PM Program dialog box
opens.
- Enter an ID for the new revision in the New
Revision field.
- Click OK.