Copy PM Program

Explanation

Use this activity to create a new PM program by copying an existing PM program. You cannot copy PM programs that belong to different sites.

Note: You can only use this activity to create new PM programs, and not to create new PM program revisions. PM program revisions are created using the Create New Revision for PM Program dialog box.

Prerequisites

System Effects

Window

PM Program

Related Window Descriptions

PM Program

Procedure

  1. Open the PM Program window, and query for the PM program you want to copy (F3).
  2. Right-click on the header of the window and then click Copy PM Program. The Copy PM Program dialog box opens, and the details of the existing PM program will be displayed in the Copy From area.
  3. Enter a new PM program ID and a revision (the revision is set to 1 by default) in the Copy To area.
  4. Click OK.